Index

51 entries

Help me choose
ModelValueOften used

Benefits map

A benefits map makes the proposed links between outputs, changed behaviour and useful outcomes explicit. Treat each link as a hypothesis to test.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A benefits map makes the proposed links between outputs, changed behaviour and useful outcomes explicit. Treat each link as a hypothesis to test.

Before using it: Define the intended outcome and who will measure it.

ModelDeliveryOften used

Choosing the delivery approach

Choose how to organise delivery by examining uncertainty, the cost of change and the feedback available. Different components of the same project can need different approaches.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: Choose how to organise delivery by examining uncertainty, the cost of change and the feedback available. Different components of the same project can need different approaches.

Before using it: Start with uncertainty, feedback and the cost of changing completed work.

ModelCommunicationOften used

Communication plan

A communication plan connects an information need to its audience, purpose, owner, timing and feedback route.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A communication plan connects an information need to its audience, purpose, owner, timing and feedback route.

Before using it: Start with the decision, audience and feedback needed.

ModelGovernanceOften used

Compliance map

A compliance map links applicable obligations to owners, delivery requirements and evidence. It helps distinguish a confirmed obligation from an assumption that needs expert review.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A compliance map links applicable obligations to owners, delivery requirements and evidence. It helps distinguish a confirmed obligation from an assumption that needs expert review.

Before using it: Identify who can decide, the constraints and the evidence needed.

ModelCostOften used

Cost aggregation

Cost aggregation rolls estimates into a coherent budget while preserving the ability to see what the totals contain.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: Cost aggregation rolls estimates into a coherent budget while preserving the ability to see what the totals contain.

Before using it: Separate work estimates, reserves and approved funding.

ModelStakeholdersOften used

Engagement gaps

An engagement-gap assessment compares current behaviour with the participation needed for a particular project decision or outcome.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: An engagement-gap assessment compares current behaviour with the participation needed for a particular project decision or outcome.

Before using it: Consider interests, influence and those affected by decisions.

ModelGovernanceOften used

Ethical decision steps

A structured ethical discussion makes competing obligations and affected people visible before a decision is justified solely by convenience or schedule.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A structured ethical discussion makes competing obligations and affected people visible before a decision is justified solely by convenience or schedule.

Before using it: Identify who can decide, the constraints and the evidence needed.

ModelGovernanceOften used

Governance levels and escalation

Governance makes decision rights explicit: who can approve what, which constraints apply and who must decide when a forecast crosses them.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: Governance makes decision rights explicit: who can approve what, which constraints apply and who must decide when a forecast crosses them.

Before using it: Identify who can decide, the constraints and the evidence needed.

ModelDeliveryOften used

Life cycles, phases and gates

A life cycle groups work into phases and defines when to reconsider the investment. A gate is a decision based on evidence, not simply a meeting on the calendar.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A life cycle groups work into phases and defines when to reconsider the investment. A gate is a decision based on evidence, not simply a meeting on the calendar.

Before using it: Start with uncertainty, feedback and the cost of changing completed work.

ModelScheduleOften used

Milestone plan

A milestone marks a verifiable state or decision in delivery. It helps coordinate commitments without pretending to be the detailed schedule.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A milestone marks a verifiable state or decision in delivery. It helps coordinate commitments without pretending to be the detailed schedule.

Before using it: Check dependencies, duration assumptions and resource availability.

ModelGovernanceOften used

RACI matrix

A responsibility matrix connects deliverables and decisions to the people doing the work, approving it, advising on it and receiving updates.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A responsibility matrix connects deliverables and decisions to the people doing the work, approving it, advising on it and receiving updates.

Before using it: Identify who can decide, the constraints and the evidence needed.

ModelCostOften used

Reserves in the budget

A reserve is funding held for uncertainty under an explicit release rule. Showing reserves separately makes the remaining exposure and decision rights visible.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A reserve is funding held for uncertainty under an explicit release rule. Showing reserves separately makes the remaining exposure and decision rights visible.

Before using it: Separate work estimates, reserves and approved funding.

ModelResourcesOften used

Resource plan

A resource plan connects the work to the skills, capacity and availability required to perform it.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A resource plan connects the work to the skills, capacity and availability required to perform it.

Before using it: Keep effort, elapsed duration and skills distinct.

ModelRiskOften used

Responses to threats and opportunities

Choose an action, an owner and a fallback for an uncertain event.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: Choose an action, an owner and a fallback for an uncertain event.

Before using it: Describe events, consequences and assumptions before assigning numbers.

ModelValueOften used

The living business case

A business case compares feasible options against a need, including doing less or doing nothing. Its purpose is to support an investment decision that can be revisited.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A business case compares feasible options against a need, including doing less or doing nothing. Its purpose is to support an investment decision that can be revisited.

Before using it: Define the intended outcome and who will measure it.

ModelScopeOften used

Work breakdown structure

A work breakdown structure decomposes agreed scope into manageable elements with boundaries and accountable owners. It organises the work; it does not by itself show its sequence.

Guide · Foundation

Fit and prerequisites

Prioritised for recurring project work: A work breakdown structure decomposes agreed scope into manageable elements with boundaries and accountable owners. It organises the work; it does not by itself show its sequence.

Before using it: Agree outcomes, boundaries and acceptance evidence.

ModelProcurementSituational

BATNA and ZOPA

Decide when to say yes and when to walk away, against your best alternative.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Decide when to say yes and when to walk away, against your best alternative.

Before using it: Use the same scope and test commercial assumptions.

ModelFlowSituational

Burn charts and velocity

Forecast, as a range, when a team will finish, and see whether a gap comes from its pace or from added scope.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Forecast, as a range, when a team will finish, and see whether a gap comes from its pace or from added scope.

Before using it: Use consistent workflow boundaries and observation periods.

ModelQualitySituational

Cause-and-effect (fishbone) diagram

Sort the possible causes of one problem into groups, so the team looks across the whole system first.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Sort the possible causes of one problem into groups, so the team looks across the whole system first.

Before using it: Agree acceptance criteria and distinguish variation from a meaningful signal.

ModelChangeSituational

Change curve

Expect how people often react to a change over time, and plan support so that the dip is shallower and shorter.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Expect how people often react to a change over time, and plan support so that the dip is shallower and shorter.

Before using it: Identify whose behaviour must change and how adoption will be observed.

ModelPeopleSituational

Choosing a response to conflict

Conflict-handling modes provide different ways to balance your own concern with another person’s concern. The useful question is which response fits the stakes, relationship and time available.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Conflict-handling modes provide different ways to balance your own concern with another person’s concern. The useful question is which response fits the stakes, relationship and time available.

Before using it: Describe observable behaviour and the context before choosing an intervention.

ModelProcurementSituational

Contract types and risk

Choose how a supplier is paid, and so who carries the cost risk, to fit how well the work is defined.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Choose how a supplier is paid, and so who carries the cost risk, to fit how well the work is defined.

Before using it: Use the same scope and test commercial assumptions.

ModelQualitySituational

Control chart

Tell normal variation from a real signal over time, so you act on special causes and change the process for the rest.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Tell normal variation from a real signal over time, so you act on special causes and change the process for the rest.

Before using it: Agree acceptance criteria and distinguish variation from a meaningful signal.

ModelPerformanceSituational

Control cycle

Compare progress and the forecast with the baseline, then correct the work or change the plan.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Compare progress and the forecast with the baseline, then correct the work or change the plan.

Before using it: Use a common baseline, measurement boundary and status date.

ModelScheduleSituational

Critical path method (CPM)

Find the chain that sets the shortest possible duration: the work whose delay moves the end date.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Find the chain that sets the shortest possible duration: the work whose delay moves the end date.

Before using it: Check dependencies, duration assumptions and resource availability.

ModelPerformanceSituational

Earned value forecasting

Earned-value forecasts estimate final cost under stated assumptions about the efficiency of remaining work. Several forecasts can be useful precisely because their assumptions differ.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Earned-value forecasts estimate final cost under stated assumptions about the efficiency of remaining work. Several forecasts can be useful precisely because their assumptions differ.

Before using it: Use a common baseline, measurement boundary and status date.

ModelPerformanceSituational

Earned value: progress and cost

Earned value compares the budgeted value of completed work with planned work and actual cost at the same status date.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Earned value compares the budgeted value of completed work with planned work and actual cost at the same status date.

Before using it: Use a common baseline, measurement boundary and status date.

ModelEstimationSituational

Estimating techniques by stage

Fit the technique to the stage and the data, and show how wide the estimate still is.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Fit the technique to the stage and the data, and show how wide the estimate still is.

Before using it: Define scope, units and the evidence behind the range.

ModelFlowSituational

Kanban board and flow

Keep a flow of work moving and predictable, by showing all of it and limiting how much is in progress at once.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Keep a flow of work moving and predictable, by showing all of it and limiting how much is in progress at once.

Before using it: Use consistent workflow boundaries and observation periods.

ModelPeopleSituational

Leadership that fits the situation

Adjust the amount of direction and support to a particular task and the person’s current familiarity with it. Agree the arrangement rather than assigning a permanent label to the person.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Adjust the amount of direction and support to a particular task and the person’s current familiarity with it. Agree the arrangement rather than assigning a permanent label to the person.

Before using it: Describe observable behaviour and the context before choosing an intervention.

ModelChangeSituational

Leading change in steps

Plan the people side of a change in an order that works: make the need felt, move with support, then make the new way last.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Plan the people side of a change in an order that works: make the need felt, move with support, then make the new way last.

Before using it: Identify whose behaviour must change and how adoption will be observed.

ModelScopeSituational

MoSCoW prioritisation

MoSCoW separates what a delivery increment must include from what is important, optional or explicitly outside this increment. It makes scope flexibility visible before time runs out.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: MoSCoW separates what a delivery increment must include from what is important, optional or explicitly outside this increment. It makes scope flexibility visible before time runs out.

Before using it: Agree outcomes, boundaries and acceptance evidence.

ModelFinanceSituational

Net present value and IRR

Judge an investment in today's money: discount each year's cash flow, add them up, and find the rate that gives zero.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Judge an investment in today's money: discount each year's cash flow, add them up, and find the rate that gives zero.

Before using it: Use consistent currency, timing and price assumptions.

ModelQualitySituational

Pareto chart

Rank the causes of a problem by count, so the team fixes first the vital few that produce most of the effect.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Rank the causes of a problem by count, so the team fixes first the vital few that produce most of the effect.

Before using it: Agree acceptance criteria and distinguish variation from a meaningful signal.

ModelFinanceSituational

Payback period

Show how long the money is at risk: the time until the cash coming back equals the cash put in.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Show how long the money is at risk: the time until the cash coming back equals the cash put in.

Before using it: Use consistent currency, timing and price assumptions.

ModelQualitySituational

Plan–do–check–act (PDCA)

Improve a process or a deliverable in small, tested steps.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Improve a process or a deliverable in small, tested steps.

Before using it: Agree acceptance criteria and distinguish variation from a meaningful signal.

ModelStakeholdersSituational

Power–interest grid

A power–interest grid helps discuss who can affect the project and who is affected by its outcome. It is a starting point for engagement, not a judgement of a person’s worth.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: A power–interest grid helps discuss who can affect the project and who is affected by its outcome. It is a starting point for engagement, not a judgement of a person’s worth.

Before using it: Consider interests, influence and those affected by decisions.

ModelDeliverySituational

Project closure checklist

End a project or a release so the result is accepted, runs in the right hands, and nothing is left open.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: End a project or a release so the result is accepted, runs in the right hands, and nothing is left open.

Before using it: Start with uncertainty, feedback and the cost of changing completed work.

ModelPeopleSituational

Psychological safety

Psychological safety concerns whether people can raise a question, concern or mistake without expecting interpersonal humiliation. It supports learning alongside clear standards of work.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Psychological safety concerns whether people can raise a question, concern or mistake without expecting interpersonal humiliation. It supports learning alongside clear standards of work.

Before using it: Describe observable behaviour and the context before choosing an intervention.

ModelQualitySituational

Quality assurance vs quality control

Keep four quality checks apart: process, deliverable, specification and real need.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Keep four quality checks apart: process, deliverable, specification and real need.

Before using it: Agree acceptance criteria and distinguish variation from a meaningful signal.

ModelPeopleSituational

Reading a developing conflict

Look at how a disagreement is changing: can people still examine the problem together, or are threats and personal attacks making a constructive exchange harder?

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Look at how a disagreement is changing: can people still examine the problem together, or are threats and personal attacks making a constructive exchange harder?

Before using it: Describe observable behaviour and the context before choosing an intervention.

ModelPeopleSituational

Reflection cycle

A reflection cycle turns an experience into a specific change you can try, instead of stopping at whether the event felt successful.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: A reflection cycle turns an experience into a specific change you can try, instead of stopping at whether the event felt successful.

Before using it: Describe observable behaviour and the context before choosing an intervention.

ModelResourcesSituational

Resource histogram and levelling

Set the people the plan needs per period against those available, and remove the overloads.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Set the people the plan needs per period against those available, and remove the overloads.

Before using it: Keep effort, elapsed duration and skills distinct.

ModelScheduleSituational

Schedule compression

Schedule compression seeks an earlier finish by changing how critical work is performed, overlapped or resourced.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Schedule compression seeks an earlier finish by changing how critical work is performed, overlapped or resourced.

Before using it: Check dependencies, duration assumptions and resource availability.

ModelCommunicationSituational

Sender–receiver model

A message passes through a channel and is interpreted by someone with their own context. Feedback tests whether the meaning received matches the meaning intended.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: A message passes through a channel and is interpreted by someone with their own context. Feedback tests whether the meaning received matches the meaning intended.

Before using it: Start with the decision, audience and feedback needed.

ModelPerformanceSituational

Status report and RAG

Tell each level where the project stands, where it is heading and what to decide, in colours read the same way.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Tell each level where the project stands, where it is heading and what to decide, in colours read the same way.

Before using it: Use a common baseline, measurement boundary and status date.

ModelPeopleSituational

Team development stages

Team-development stages offer a vocabulary for discussing how a group establishes working relationships and ways of delivering together. They describe a possible pattern, not a required timetable.

Guide · Foundation

Fit and prerequisites

Use when this specific decision arises: Team-development stages offer a vocabulary for discussing how a group establishes working relationships and ways of delivering together. They describe a possible pattern, not a required timetable.

Before using it: Describe observable behaviour and the context before choosing an intervention.

ModelChangeSituational

The change control route

Change a baseline only by decision: the impact known, and the right level deciding.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Change a baseline only by decision: the impact known, and the right level deciding.

Before using it: Identify whose behaviour must change and how adoption will be observed.

ModelDeliverySituational

The Scrum cycle

Deliver in short, fixed cycles, and after each one inspect and adapt.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Deliver in short, fixed cycles, and after each one inspect and adapt.

Before using it: Start with uncertainty, feedback and the cost of changing completed work.

ModelEstimationSituational

Three-point estimate (PERT)

Replace a single guess with a range: an expected value and a spread that show how sure the estimate is.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: Replace a single guess with a range: an expected value and a spread that show how sure the estimate is.

Before using it: Define scope, units and the evidence behind the range.

ModelScheduleSituational

Total float and free float

How long each activity can slip before the end date moves, or before the next activity must wait.

Study sheet · Foundation

Fit and prerequisites

Use when this specific decision arises: How long each activity can slip before the end date moves, or before the next activity must wait.

Before using it: Check dependencies, duration assumptions and resource availability.