When to use it

A useful fit

Use it before committing resources and whenever the expected benefit, cost, risk or strategic need changes materially.

Know the limits

Do not treat past spending as a reason to continue. Separate unavoidable future costs from costs you can still avoid.

How to use it

  1. State the need and credible alternatives, including the minimum viable change.
  2. Compare future costs, benefits, assumptions and risks on a consistent basis.
  3. Name a benefit owner and a review trigger that could change the decision.

Worked example

A support team considers replacing a case-management tool. The sponsor compares replacement, targeted improvements and retaining the current tool. When a required integration becomes unavailable, the team reopens the options before authorising migration.

Illustrative scenario by fannarmaximus; not an official exam question.

Common pitfalls

A positive headline benefit is weak evidence if nobody owns adoption or can show how the benefit will be measured.

Attribution & sources

Common investment-governance practice; own-word explanation by fannarmaximus.

The citations below identify authoritative references for this topic. They do not imply endorsement or reproduce the bodies’ competence lists.

  • IPMA® (2015). Individual Competence Baseline for Project, Programme and Portfolio Management, Version 4.0 (ICB4). Zurich: International Project Management Association. ISBN 978-94-92338-00-6 (print), 978-94-92338-01-3 (pdf). Free PDF from IPMA®: https://ipma.world/ipma-standards-development-programme/icb4/
  • Project Management Institute (2025). A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Eighth Edition, and The Standard for Project Management. Newtown Square, PA: PMI®. ISBN 9781628258295.
  • Association for Project Management (2025). APM Body of Knowledge, 8th edition. Princes Risborough: APM. ISBN 9781913305390.

Learn and apply

Explore value: guides, calculations and sources