When to use it

A useful fit

Use it to challenge a forecast and discuss which performance pattern is likely to persist.

Know the limits

Do not select the most reassuring formula without a delivery explanation. Re-estimate the remaining work when the baseline is no longer credible.

How to use it

  1. Check the baseline, completion rules and completeness of actual costs.
  2. Choose an assumption: performance continues, the rest follows plan, or a fresh bottom-up estimate is needed.
  3. Compare the forecast with the authorised budget and explain the causes and options to the decision owner.

Worked example

A project attributes an overrun to a one-off setup problem. The manager compares a forecast that assumes planned efficiency from now on with one that continues current efficiency, then tests the claim against the remaining work packages.

Illustrative scenario by fannarmaximus; not an official exam question.

Common pitfalls

A computed forecast is not a replacement for knowledge of contracts, remaining scope and dependencies.

Attribution & sources

Common earned-value forecasting practice; the explanation and example are by fannarmaximus.

The citations below identify authoritative references for this topic. They do not imply endorsement or reproduce the bodies’ competence lists.

  • Morris, P. W. G. (2013). Reconstructing Project Management. Chichester: Wiley-Blackwell. ISBN 9780470659076. https://doi.org/10.1002/9781118536698
  • Project Management Institute (2025). A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Eighth Edition, and The Standard for Project Management. Newtown Square, PA: PMI®. ISBN 9781628258295.

Learn and apply

Explore performance: guides, calculations and sources