When to use it

Use it as a cost-efficiency indicator where actual cost and completion measures are reliable.

Check before calculating

The ratio is undefined when actual cost is zero. Do not turn missing cost data into a zero-cost success.

  1. Define the scope, status date and units before collecting the inputs.
  2. Substitute the values into the formula and retain their units.
  3. Interpret the result against the assumptions and decide what evidence or action is needed next.

Formula & inputs

CPI = EV ÷ AC

EV is earned value and AC is actual cost; AC must be greater than zero.

Worked example

A delivery project has budget at completion of €900,000. At the same status date, planned value is €450,000, earned value is €360,000 and actual cost is €400,000. All values use the same scope and price basis.

€360,000 ÷ €400,000 = 0.90

Each euro spent has earned less than a euro of budgeted work. A forecast using this ratio assumes that the same pattern continues.

Common pitfall

The ratio can be distorted by timing differences between crediting work and recognising cost.

Source & related material

Standard quantitative technique; this explanation is by fannarmaximus. No single inventor is claimed. The arithmetic is computed from explicit inputs, not copied from an official sample question.

APM: earned-value guidance

Learn and apply

Explore performance: guides, calculations and sources