When to use it
Use integrated analysis when schedule delay changes cost or exposure materially.
Independent cost sums cannot reproduce schedule-path switching or shared-resource delays.
Apply it
- Validate the deterministic network and cost boundary.
- Model uncertain inputs and their common causes explicitly.
- Compare forecast percentiles with risk appetite and response options.
An example in practice
Delayed access prolongs both equipment rental and staff effort. Model that shared driver instead of treating the costs as independent risks.