When to use it

Use explicit completion rules before reporting earned value or progress.

When to be cautious

Time spent and money spent are not reliable substitutes for completed scope.

Apply it

Weighted completion = Σ(milestone weight × completion credit) / Σ weights

Weights must be agreed before reporting. Credits need observable acceptance evidence; this is not a measure of time consumed.

  1. Define a deliverable and its acceptance evidence.
  2. Choose a consistent milestone, unit-count or completion-credit rule.
  3. Apply it at each status date and reconcile it with actual cost.

An example in practice

Credit a migrated system after the agreed validation has passed, not when the team has consumed its allocated hours.

Source & credit

Standard estimating practice; the cited guide documents use rather than claiming invention.

GAO: Cost Estimating and Assessment Guide

This explanation and example are independently written. The source is a reading reference; linking it does not grant permission to reuse its text, figures or assessments.

Learn and apply

Explore performance: guides, calculations and sources