When to use it

Use it to find demand peaks that a task list conceals.

When to be cautious

A total headcount can hide a scarce skill or equipment conflict.

Apply it

Period demand = Σ effort assigned within that period

Compare demand and usable availability by skill and period. Total project effort can conceal a short local overload.

  1. Assign effort and resource requirements to scheduled work.
  2. Aggregate demand by resource and time window.
  3. Compare with confirmed usable availability and resolve overloads.

Try a related calculator

An example in practice

Several tasks need the same reviewer in the same week. Their combined demand exceeds capacity even though the overall staffing total seems sufficient.

Source & credit

Common scheduling practice. The critical-path method is associated with James E. Kelley Jr. and Morgan R. Walker; their 1959 paper is the historical reference.

GAO: Schedule Assessment Guide

This explanation and example are independently written. The source is a reading reference; linking it does not grant permission to reuse its text, figures or assessments.