When to use it

Use smoothing within available float; consider levelling when resource limits require date changes.

When to be cautious

Do not hide a slipped finish or violate a dependency simply to flatten a chart.

Apply it

  1. Find overloads in the resource-loaded schedule.
  2. Try movement within float, then evaluate other sequencing or capacity changes.
  3. Recompute the finish, risk and critical path after the adjustment.

Try a related calculator

An example in practice

Move non-controlling test preparation within its float to free the specialist for a controlling review.

Source & credit

Common scheduling practice. The critical-path method is associated with James E. Kelley Jr. and Morgan R. Walker; their 1959 paper is the historical reference.

GAO: Schedule Assessment Guide

This explanation and example are independently written. The source is a reading reference; linking it does not grant permission to reuse its text, figures or assessments.