When to use it

Use a maturity statement to prevent an early estimate being treated as a firm commitment.

When to be cautious

Do not copy a proprietary estimate-class table or apply a standard accuracy range across unrelated industries.

Apply it

  1. Record what is known about quantities, design and delivery conditions.
  2. State the estimation method, exclusions and uncertainty drivers.
  3. Update the range as definition and evidence improve.

An example in practice

A concept option has uncertain ground conditions. Report the assumption and investigation needed rather than attaching a false precision band.

Source & credit

Standard estimating practice; the cited guide documents use rather than claiming invention.