When to use it

Use it for a consistently measured backlog over time.

When to be cautious

A straight trend line is not a promise; changed scope and work-size variation can dominate it.

Apply it

Remaining scope = total current scope − completed scope

Keep scope changes separate from delivery progress. A straight-line extension assumes a continuing rate and stable scope.

  1. Define completion and a stable counting unit.
  2. Retain historical totals and show scope additions separately.
  3. Compare rate-based scenarios with dependencies and remaining work.

Try a related calculator

An example in practice

A burnup shows steady completion while the total scope rises faster. Discuss scope decisions rather than blaming the delivery rate.

Source & credit

Standard estimating practice; the cited guide documents use rather than claiming invention.

GAO: Cost Estimating and Assessment Guide

This explanation and example are independently written. The source is a reading reference; linking it does not grant permission to reuse its text, figures or assessments.