Before you start: Read cost, schedule and completion measurement.
Try it
EV is 360,000 and AC is 400,000. What is CPI, and can it establish the finish date?
Your reasoning, assumptions and units:
Apply it to your work
Describe a comparable situation. What evidence would you need before using this reasoning to make a decision?
Your example and next check:
Answer and reasoning
CPI = 360,000 ÷ 400,000 = 0.90. It describes cost efficiency on a consistent measurement basis. It does not establish a completion date; inspect dependencies and the schedule.
This is an independent teaching exercise, not an official exam question. Expand the answer before printing if you want it included. Your written answers are not collected by this site.