EV is 360,000 and AC is 400,000. What is CPI, and can it establish the finish date?

Your reasoning, assumptions and units:

Apply it to your work

Describe a comparable situation. What evidence would you need before using this reasoning to make a decision?

Your example and next check:

Answer and reasoning

CPI = 360,000 ÷ 400,000 = 0.90. It describes cost efficiency on a consistent measurement basis. It does not establish a completion date; inspect dependencies and the schedule.