Before you start: Use the same scope and units for all estimates.
Try it
Optimistic, most likely and pessimistic durations are 2, 5 and 14 days. What is the PERT-style mean?
Your reasoning, assumptions and units:
Apply it to your work
Describe a comparable situation. What evidence would you need before using this reasoning to make a decision?
Your example and next check:
Answer and reasoning
(2 + 4 × 5 + 14) ÷ 6 = 6 days. The triangular mean is 7 days. Both depend on assumptions and neither is a guaranteed finish date.