Before you start: Know the acceptance criteria and the future operational owner.

Try it

A sponsor accepts the deliverable, but operations has no support owner or training. Is handover complete?

Your reasoning, assumptions and units:

Apply it to your work

Describe a comparable situation. What evidence would you need before using this reasoning to make a decision?

Your example and next check:

Answer and reasoning

No. Acceptance and operational readiness are different checks. Agree ownership, training, support, remaining issues and the evidence required for transition before closing the handover.

Explore the related tools

This is an independent teaching exercise, not an official exam question. Expand the answer before printing if you want it included. Your written answers are not collected by this site.